Once the rubblized concrete has been compacted and tested, crews will place new asphalt layers on top.
Article content Rubblization is likely a term that most Prince Edward County residents aren’t that familiar with. However, that will change soon as the structural rehabilitation of County Road 49 gets underway to repair the crumbling concrete surface. Recommended Videos Starting later this month, the county’s contractor R.W. Tomlinson Ltd. will begin rubblization on County Road 49, a technique that involves breaking the existing concrete road into small pieces and leaving them in place, creating a strong foundation for the new asphalt road.
Although rubblization won’t start until later this month, construction is planned to commence this week when the contractor will begin by replacing road cross culverts. Motorists can expect minor traffic delays as the work zones will be relatively short. Replacement of all culverts is estimated to take four weeks, said the county in a news release.
How it Works Step 1: Break the concrete A specialized pavement breaker will deliver high frequency, low-amplitude energy that will break up the brittle concrete. The concrete remains in place rather than being removed and hauled away, creating the granular base for the new asphalt road. Step 2: Compact the broken material Heavy rollers will compact the broken concrete.
This creates a stable layer that behaves more like aggregate (crushed stone) than rigid concrete. Step 3: Add new asphalt Once the rubblized concrete has been compacted and tested, crews will place new asphalt layers on top. For County Road 49, the municipality intends to place three layers of asphalt.
The municipality is aiming to place two layers of asphalt over the entire length of County Road 49 in 2026, followed by a final layer in 2027. Benefits of rubblization Using the rubblization technique is widely considered a major step forward for sustainable infrastructure featuring one hundred per cent in-place recycling: the existing concrete roadway is never sent to a landfill. This helps reduce the demand for new aggregate (crushed stone).
It will also reduce the carbon footprint with on-site recycling of the old concrete eliminates the heavy greenhouse gas emissions, fuel consumption, and traffic congestion associated with hauling away the rubble and trucking in new crushed stone. When a new hot-mix asphalt overlay is placed directly over a rubblized base, the interlocking angular concrete fragments prevent the old cracks from reflecting through to the new surface. Overall, this technique will help lower costs to taxpayers and allow for a faster rehabilitation.
Project staging The major structural rehabilitation of County Road 49 is expected to begin mid to late July. Crews will start at County Road 15 (Northport Road) and work their way south. Crews will be on site Monday – Friday, 7 a.m. to 7 p.m.
The contractor intends to rehabilitate County Road 49 in sections approximately one to two kilometres in length. A minimum of one lane of traffic, operating under alternating directions, will be maintained at all times The rubblizing machine will break up the concrete in one lane for approximately one to two kilometres. Crews will come behind to compact and level out the road, followed by a layer of new granular material.
When that lane of road is complete, crews will turn and work back in the other direction and repeat the process on the adjacent lane. Once both lanes have been rubblized and a new layer of granular material has been placed, the base lift of asphalt will be placed over both lanes. Drivers can expect delays of between five to 10 minutes.
Both lanes of traffic will re-open at the end each construction day and on weekends. Calcium chloride will be applied to the gravel sections of the road to suppress the dust.
- Published
- Jul 13, 2026
- Updated
- Jul 13, 2026
- Source
- Intelligencer
- Category
- Environment
- Read time
- 3 min
Key facts
Why this matters locally
This environment story matters locally because it may affect readers, businesses, commuters, families, or public services in British Columbia.
Local impact
BC Post links this item to British Columbia coverage so readers can follow related city updates, weather, traffic, events, and category news in one place.
Timeline
Source and credit
BC Post may summarize, organize, and add local context for reader clarity. Original reporting remains with the listed publisher.