A certificate of public convenience and necessity will not be required for BC Hydro’s South Peace System Reinforcement Project, under an exemption announced by the Government of B.C.
The project is intended to add electricity capacity in the South Peace region for new or expanded natural-gas production and processing facilities. The Government of British Columbia says the additional capacity could support up to $3 billion in industrial investment and contribute as much as $8.8 billion to gross domestic product over the lifetime of the developments.
BC Hydro plans to upgrade the Dawson Creek and Bear Mountain substations and increase the operating voltage of two existing 12-kilometre, 138-kilovolt transmission lines between them to 230 kilovolts. The project is planned without constructing new transmission lines.
NorthRiver Midstream plans to expand the West Doe Gas Plant northwest of Dawson Creek, raising its processing capacity from 100 million to 400 million cubic feet per day. The Government of British Columbia release puts the expansion’s estimated capital cost at $500 million.
BC Hydro is scheduled to start the transmission upgrades in 2028, with the project expected to be in service in 2030. The government says the added capacity could also support projects planned by NorthRiver Midstream, Tourmaline, ARC Resources and Shell.